Discussion Post: Beta Distribution
You are the project manager for the Sweep Time software project. You have decided to use the beta distribution, or 3-point estimation, technique for this project. For the "phase 1 test" activity in days, the following estimates are available: O=5, P=10, M=6.
Address the following:
a) Explain beta distribution, when it is used, and the benefits and shortcomings of the technique.
b) What is the result of this estimate in the example?
c) How does a skew from the mean/median figure relate to planning a project? That is, if your beta is 7.5 and your M=6, how do these relate?
The response must include a reference list. Using Times New Roman 12 pnt font, double-space, one-inch margins, and APA style of writing and citations.