What is the reliability of the following parallel


1. What is the reliability of the following parallel production process? R1 = 0.95, R2 = 0.90, R3 = 0.98.

301_Figure.png

2. What is the overall reliability that bank loans will be processed accurately if each of the 5 clerks shown in the chart has the reliability shown?

1829_Figure1.png

Hint: The three paths are done in parallel, followed by an additional independent step.