A project is expected to create operating cash flows of $231,000 a year for five years. The initial cost of the fixed assets is $564,000. These assets will be worthless at the end of the project. An additional $34,500 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of return is 15 percent?