Masulis Inc. is considering a project that has the following cash flow and WACC data.

What is the project's discounted payback?

WACC: 10.00%

Year 0 1 2 3 4

Cash flows -$925 $525 $485 $445 $405

a. 2.14 years

b. 2.40 years

c. 1.95 years

d. 2.25 years

e. 1.86 years