What is the projects approximate err


Question: A project pays off $2,501 right away, has $ 5,511 in costs at the end of the second year and again pays off 3,688 at the end of the third year. If MARR is 30 %, what is the project's approximate ERR?

(Note: Give your answer in percentages without % sign and keep two decimal places)