Problem
Collecting requirements for the project and creating the WBS has been a daunting task because stakeholders' needs are vague and are only expressed in the most general terms due to the nature of the project. As a result of this uncertainty, the project manager is concerned about excessive changes, wasted work, and rework anticipated during project execution.
What is the project manager's best course of action?