A project consists of four activities: A, B, C, and D. 1.C follows A. 2.D follows B and C. The durations of each are A=4, B=6, C=3, D= 3 days. Answer the following questions.a) What is the project duration? b) What is the critical path? c) Which activities can be delayed, and for how many days?