Problem:
Vespucci is adding a project to the company portfolio and has the following information: the expected market return is 16.5%, the risk-free rate is 3.7%, and the expected return on the new project is 14.6%.
Required:
Question: What is the project's beta?
Note: Please show guided help with steps and answer.