What is the production wheel turn time


A plant makes five products in a single cell, we will call them products A, B, C, D, and E. The following information is known:

o Changeovers between the products are done on the fly.
o There is a five-hour cleanout at the end of the complete five-product cycle.
o Maintenance requires five percent of the available work time.
o Human factor downtime adds another five percent to outage.
o Daily demand is 8,000 units (of all products combined).
o Production rate is 20,000 per day.

What is the production wheel turn time?