Complete the multiple choice questions:
Q1: A project was planned using PERT with three time estimates. The expected completion time of the project was determined to be 40 weeks. The variance of the critical path is 9. What is the probability that the project will be finished in 46 weeks or less?
A. 2%
B. 73%
C. 98%
D. impossible to determine with this information
Q2: The project manager wishes to set the due date for the completion of the project so that there is 90% chance of finishing on schedule. Thus, there would only be a 10% chance the project would take longer than this due date. What should this due date be?
A. 40.25 weeks
B. 43.84 weeks
C. 51.13 weeks
D. 60 weeks