Question: Two software companies, Micro Ware and BusiCorp, are preparing a new business package in time for a computer trade show 180 days in the future. They work independently. Micro Ware has anticipated completion time, in days, exponential (1/150). BusiCorp has time to completion, in days, exponential (1/130). What is the probability both will complete on time; that at least one will complete on time; that neither will complete on time?