Question: A machine operator stamps labels on sheets of metal that are later made into cans. Each sheet can make 118 cans. The cost per sheet of metal is $10.60. The operator is paid $9.40 per hour and labels 120 sheets per hour. What is the prime cost of labeling 1 can?