What is the present value of the following planned cash flow for a 25 year power plant project? Assume that the annual cost of money is 4.2%. Draw the cash flow diagram and present your solution. Initial Investment (construction costs) - $60,000,000 Annual operating costs - $750,000 Annual maintenance costs - $95,000 Projected decommissioning expenses – $13,000,000 Projected income from scrap - $350,000.