Problem 1: You will be the project manager of a project that has not received final approval. you have identified several stakeholders an you know that there are more. You can identify stakeholders during what process groups?

a. executing, monitoring & controlling and closing

b. initiating and planning

c. initiating

d. all five process groups

Problem 2: In a project, a cost incentive contact has been awarded to a contract with the following parameters:

Target cost: 1,000,000

Target contractor fee: 100,000

Cost benefit sharing ratio: 80%/20%

Price Ceiling: 1,200,000

What is the point of total assumption (PTA, breakpoint) of the project?