What is the planned duration for the testing project


Assignment

Your team has been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows:

Create a testing plan

Once the testing plan is ready, your team can:

1) Test the user interfaces
2) Test the database
3) Test the network
4) Write the documentation first draft

When the user interface tests are complete, you can:

1) Perform user testing-enlist some users to test the user interface

When the database and network testing are complete, you can:

2) Perform integration testing-network with the database

When the user testing of the user interface and the database testing are complete, you can:

3) Perform integration testing-database, network, and user interface

When all integration testing and user testing are complete, you can:

4) Perform system testing

Then you can:

5) Review and revise documentation

After all other tasks are complete, you can:

6) Obtain management approval

Duration estimates for the tasks:

• 3 days
• 10 days
• 6 days
• 7 days
• 20 days
• 5 days
• 3 days
• 2 days
• 8 days
• 4 days
• 5 days

Create a network diagram and a Gantt chart for the project tasks. Ask your instructor if you are permitted to use software such as Microsoft Project to help you prepare your diagrams.

1) What is the planned duration for the testing project?

2) What is the critical path for the testing project?

3) For each task NOT on the critical path, calculate the amount of slack available.

4) If the user testing of the user interface takes 15 days, what will the impact be on the project duration?

Format your assignment according to the following formatting requirements:

(1) The answer should be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

(2) The response also includes a cover page containing the title of the assignment, the student's name, the course title, and the date. The cover page is not included in the required page length.

(3) Also include a reference page. The Citations and references should follow APA format. The reference page is not included in the required page length.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the planned duration for the testing project
Reference No:- TGS03122059

Expected delivery within 24 Hours