Assignment:
A production line has four workstations and a 50-second cycle time. The total amount of actual task time across all four workstations is 170 seconds. What is the idle time? The percent idle time? The efficiency delay? Polar Containers makes high-end coolers for camping. The total task time needed to make a cooler is 360 seconds, with the longest individual task taking 50 seconds.