Problem

What is the optimum number of stations if you want to produce 4,500 PDAs per workday assuming 7.5 hours per day using these tasks?

Work Task

Time (seconds)

1

2.0

2

3.0

3

1.0

4

5.0

5

2.5

6

2.0

7

4.0

8

4.0

9

2.0

10

5.5

TOTAL

31 seconds


Compute efficiency of original line and the line you've assessed as optimum efficiency.