What is the optimal sequence for the jobs to be scheduled


Problem

The following set o five jobs is to be processed through two work centers (WC's). The sequence is WC 1 to WC 2. Processing time for each of the work centers is shown in the following table: Job T U V W X Work Center 1 15, 7, 4, 7, 10. Work Center 2. 3, 9, 10, 6, 9

What is the optimal sequence for those jobs to be scheduled? Chart these jobs through the two work centers What is the total time of the whole operation? What are the idle times of each work center?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the optimal sequence for the jobs to be scheduled
Reference No:- TGS03289833

Expected delivery within 24 Hours