$75,000 has been spent for developing the system. There has been no benefit to the organization in year 0. Years 1 thru 5 cost are expected to be $25,000 each year.
Benefits for years 1 thru 5 are expected to be $50,000 each year.
The discount rate for this organization is 10%. What is the NPV and ROI