Discuss the below in detail:
Q: A production operation is a single-channel, single-phase, unlimited-queue-length queuing system. Products arrive at the operation at an average rate of 30 per hour, and the present average production rate is 33 products per hour. Management wants products to be at the operation an average of only .1 hour. What is the new average production rate at the operation?