A project for improving a billing process has the following precedence relationships and activity times :
Activity
|
Activity Time(weeks)
|
Immediate Predecessor(s)
|
A
|
5
|
-
|
B
|
9
|
-
|
C
|
6
|
A
|
D
|
12
|
B,C
|
E
|
9
|
B
|
F
|
5
|
D
|
G
|
3
|
E
|
h
|
6
|
F,G
|
What is the network diagram?
Calculate the slack for each activity. Which activites are on the critical path?