Question: What is the net present value (discounted at 8%) of this project? Consider all costs and expected revenues Development cost $ 950,000 Estimated development time 9 months Pilot testing $ 200,000 Ramp-up cost $ 400,000 Marketing and support cost $ 150,000 per year Sales and production volume 60,000 per year Unit production cost $ 100 Unit price $ 175 Interest rate 8