What is the net present value of a project with the


What is the net present value of a project with the following cash flows if the discount rate is 15%?

Year 0 = -$39,400

Year 1 = $12,800

Year 2 = $21,700

Year 3 = $18,100

a. $39.80

b. $42.97

c. $44.16

d. $48.21

e. $48.30

Project has the following cash flows. What is the payback period?

Year 0 = -$92,000

Year 1 = $27,000

Year 2 = $45,800

Year 3 = $16,800

Year 4 = $11,200

a. 2.48 years

b. 2.59 years

c. 2.96 years

d. 3.21 years

e. 3.43 years