What is the net present value of a project with the following cash flows if the discount rate is 15%?
Year 0 = -$39,400
Year 1 = $12,800
Year 2 = $21,700
Year 3 = $18,100
a. $39.80
b. $42.97
c. $44.16
d. $48.21
e. $48.30
Project has the following cash flows. What is the payback period?
Year 0 = -$92,000
Year 1 = $27,000
Year 2 = $45,800
Year 3 = $16,800
Year 4 = $11,200
a. 2.48 years
b. 2.59 years
c. 2.96 years
d. 3.21 years
e. 3.43 years