Brooksold Corporation contracts to have Zealent Construction Company build a factory for $4,000,000. Days before the start of construction, Zealent withdraws from the contract. Brooksold invites proposals for the construction and contracts with Sierra Nos Builders for $3,800,000. Can Brooksold hold Zealent liable for nonperformance? What can the company recover as compensation for damages?
Discuss circumstances under which a breaching party is not liable to pay consequential damages to a nonbreaching party?