A city is trying to estimate the most money it should offer to contractors as an incentive for them to finish a disruptive road project early. The transportation project lengthens transport times by 10 hours per week for 40,000 workers. Assume that all workers are paid $10 per hour in a perfectly competitive labor market. What is the most that the city should pay to the contractors as an incentive for completing the project four weeks early?