Discuss the folloiwng:
Q1. How many activities are included in the monthly budget for month four? (note: the ES, LS, and t are presented in months)
A. 1 B. 2 C. 3 D. impossible to tell
Q2. What is the monthly budget for month 16 of this project, using earliest start times?
A. 3127 B. 2290 C. 1617 D. 714
Q3. For the monthly budgets using earliest start times, which of these months has the largest monthly budget?
A. 10 B. 19 C. 24 D. 36
Q4. Which activity has the largest budget?
A. A B. B C. E D. I E. M
Q5. Using the latest start times to determine monthly budgets, what month would you begin activity F?
A. 13 B. 14 C. 15 D. 16
Q6. Using the latest start times to figure the monthly budgets, which of these months has the smallest budget?
A. 1 B. 10 C. 25 D. 36
Fred Ridgeway has been given the responsibility of managing a training and development program. He mows the earliest start time, them latest start time, and :he total costs for each activity. This information is Oven in the following table: