1. Allen Machines specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds. Allen Machines is contemplating the construction of a machine that would harvest weeds on narrow rivers and waterways. The activities and time in weeks necessary to build one of these experimental machines are shown in the table below.
Activity
|
Immediate Predecessors
|
Time in Weeks
|
A
|
none
|
6
|
B
|
none
|
5
|
C
|
A
|
3
|
D
|
A
|
2
|
E
|
B
|
4
|
F
|
B
|
6
|
G
|
C,E
|
10
|
H
|
D,F
|
7
|
1. What is the minimum possible time required for completing the project?
2. What is the latest possible time that Activity D may be started without delaying the completion of the project?
3. What is the latest finish time for Activity F?
4. What is/are the critical path(s)?