1. Your plant wants to order new machines for a process that totals 360 seconds. The demand for a typical 7.4 hour day is 60.
What is the minimum number of machines to be ordered?
2. What's the difference between line authority and staff authority?
3. Explain the three traditional organizational designs? Quote examples.