An assembly line with 9 tasks is to be balanced.
The longest task takes 7.5 minutes to complete, and the total time for all tasks is 26.3 minutes. The line operates 470 minutes per day.
What is the minimum cycle time in this configuration?
(Your answer should be in minutes and contain one decimal place)