Problem: What is the minimum cost of crashing the following project by 4 days?
|
Normal
|
Crash Time
|
Normal
|
Crash
|
Immediate
|
Activity
|
Time (days)
|
(days)
|
Cost
|
Cost
|
Predecessor(s)
|
|
|
|
|
|
|
A
|
6
|
5
|
$ 900
|
$1,300
|
-
|
B
|
8
|
6
|
300
|
800
|
-
|
C
|
4
|
3
|
500
|
700
|
-
|
D
|
5
|
3
|
900
|
1,900
|
A
|
E
|
8
|
5
|
1,000
|
1,900
|
C
|