Assignment:
A medical equipment manufacturer subjected 100 pacemakers to 5000 hours of testing (all running simultaneously). Four of them failed after: 1,140 hrs 2,337 hrs 3,699 hrs and 4,254 hrs of operation respectively. What is the mean time before failure (MTBF) of these types of pacemakers (calculate to rounded hours).