What is the maximum potential profit


Response to the following:

(1) Consider a small production system for manufacturing two products, X and Y as shown below. Manufacturing X requires two raw materials (RM 1 and 2). Manufacturing Y also requires two raw materials (RM 2 and 3). In addition, Y uses a purchased component that costs $10 per unit. Four work centers (A, B, C, and D) are used to manufacture the products. Each has 7,200 minutes (120 hours; 3-eight hour shifts) available each week. Operating expenses for the week, including everything except materials costs, is $12,000.

                                      X                Y

Demand per week         300 units    150 units

Selling price                $180/unit     $200/unit

Raw material costs (per unit)

RM 1                          $40

RM 2                          $40             $40

RM 3                                            $40

Purchased parts                             $10

Time available on each work center is 7,200 minutes.

(a) What is the maximum potential profit of the production system?

(b) Find the bottleneck work center. Show why it is a constraint.

(c) What is the maximum feasible amount of profit subject to the constraint?

(d) The manager plans to purchase a new technology at $750,000 to reduce the processing time on both RM 2 and RM 3 at the bottleneck workstation by half. What would you say about his plan? Discuss.

Attachment:- refer.rar

Solution Preview :

Prepared by a verified Expert
Cost Accounting: What is the maximum potential profit
Reference No:- TGS01853854

Now Priced at $25 (50% Discount)

Recommended (92%)

Rated (4.4/5)