What is the materials price variance for july


The Porter Company has a standard cost system. In July the company purchased and used 22,500 pounds of direct material at an actual cost of $53,000; the materials quantity variance was $1,875 Unfavorable; and the standard quantity of materials allwed for July production was 21,750 pounds. What is the materials price variance for July?