For project A, the cash flow effect from the change in net working capital is expected to be -700 dollars at time 2 and the level of net working capital is expected to be 2,200 dollars at time 2. What is the level of current assets for project A expected to be at time 1 if the level of current liabilities for project A is expected to be 5,000 dollars at time 1?