Problem
The network below represents a project being analyzed by the critical path method.
Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6.
1. What is the critical path of this network?
2. What is the length of the critical path?
3. What is slack time at activity H?
4. What is the Late Finish of activity H?
5. If activity C were delayed by two time units, what would happen to the project duration?