Problem: You completed mapping the current state. Your customers take 15 days to receive the delivery of the product from the time of its order. It takes 3 hours to produce one unit of the product to meet the customer requirements. The approximate amount of time required to handle a process in the production step is1.5hours.
What is the Lead Time of this process?