A project has the following cash flows:
Year Cash Flow
0 $ 69,500
1 – 47,000
2 – 30,400
Requirement 1: What is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) Internal rate of return %
Requirement 2: What is the NPV of this project if the required return is 6 percent? (Do not round intermediate calculations. Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).) Net present value $
Requirement 3: What is the NPV of the project if the required return is 0 percent? (Do not round intermediate calculations. Negative amount should be indicated by a minus sign. Round your answer to 2 decimal places (e.g., 32.16).) Net present value $
Requirement 4: What is the NPV of the project if the required return is 23 percent? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g.,32.16).) Net present value $