An assembly line currently has five workstations and the time required for each is shown below. 1: 48 seconds, 2: 38 seconds, 3: 44 seconds, 4: 56 seconds, 5: 42 seconds What is the efficiency of the process? What is the hourly production rate of the current process Customer demand is 90 units per hour. What does the cycle time need to be to be able to meet demand (what is the takt time)?