What is the float for activity


The following data were obtained from a project to create a new portable electronic.

Activity Duration Predecessors
A 3 Days ---
B 4 Days ---
C 6 Days ---
D 2 Days A, B
E 1 Days C
F 3 Days D
G 3 Days E, F
H 7 Days D
I 10 Days G

Construct a network for the project.

(A.) What is the Scheduled Completion of the Project?
(B.) What is the Critical Path of the Project?
(C.) What is the EST for Activity D?
(D.) What is the LST for Activity G?
(E.) What is the EF for Activity B?
(F.) What is the LF for Activity H?
(G.) What is the float for Activity I?