Problem:
The following represents a project that should be scheduled using CPM:
Activity |
immed press |
A |
M |
B |
A |
|
1 |
3 |
5 |
B |
|
1 |
2 |
3 |
C |
A |
1 |
2 |
3 |
D |
A |
2 |
3 |
4 |
E |
B |
3 |
4 |
11 |
F |
C, D |
3 |
4 |
5 |
G |
D, E |
1 |
4 |
6 |
H |
F, G |
2 |
4 |
5 |
Required:
Question 1) Draw the network.
Question 2) What is the critical path?
Question 3) What is the expected project completion time?
Question 4) What is the probability of completing this project within 16 days?
Solve the given numerical problem and illustrate step by step calculation