What is the expected price of the material


The SuperFlyer Corporation is developing a revolutionary flying disc. The new toy can fly straight over a great distance, which is exciting by itself. However, this disc will also return to the owner in response to their voice! Because this is an advance over anything that this company has done before, estimating the amount and cost of the hi-tech materials are difficult. The project manager recommends using a range estimating process to develop an estimate. The values below are submitted by the project team.

Current estimates for cost of material are as follows:
Optimistic cost of smart resin: $8.00 per lb
Most likely cost of smart resin: $9.25 per lb
Pessimistic cost of smart resin: $12.50 per lb


Current estimates for total material requirements are as follows:
Optimistic quantity: 15 lb/ 100 units
Most likely quantity: 19 lb/ 100 units
Pessimistic quantity: 22 lb/ 100 units

(a) What is the expected price of the material per pound?
(b) What is the expected amount of material needed for 100 units?
(c) What is the expected cost for 100 units using the Simple Method?