What is the expected duration of activity


Problem:

A project has been defined to contain the following activities, along with their time estimates for completion. Carry three decimals in your calculations and answer the following questions:

Activity    Time Estimates (weeks)    Immediate Predecessors
a    m    b
A    2    5    6    -
B    1    5    11    -
C    4    6    10    A
D    2    2    2      B
E     1    2    9     A
F     2    4    5    C,D
G    3    8    11    C,E
H    1    2    4      F,G

a. What is the expected duration of activity H?

b. What is the variance of activity H time?

c. Using the expected activity durations, which activities form the critical path?

d. What is the probability of completing the critical path found in (C) above in 22 weeks or less?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: What is the expected duration of activity
Reference No:- TGS01940680

Now Priced at $25 (50% Discount)

Recommended (98%)

Rated (4.3/5)