A small project consists of three activities: A, B, and C. To start activity C, both activities A and B need to be complete. Activity A takes 3 days with a probability of 50 percent and 5 days with a probability of 50 percent, and so does Activity B. Activity C takes 1 day. What is the expected completion time of the project?