Assignment:
a. The following table represents a plan for a project:
b. Indicate the critical path.
- 1-2-5-8
- 1-4-7-10-11
- 1-3-6-8-9-11
- 1-2-5-8-9-11
c. What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
d. You can accomplish any one of the following at an additional cost of $1,500. If you will save $1,000 for each day that the earliest completion time is reuced, which of the following actions should be taken, if any?
1. Reduce job 5 by two days
2. Reduce job 6 by two days.
3. Reduce job 7 by four days.