Activity Problem
Activity 1
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
Activity Description Predecessors Duration (Days)
Activity
|
Description
|
Predecessors
|
Duration (Days)
|
A
|
Site selection
|
None
|
4
|
B
|
Buy concessions
|
A
|
4
|
C
|
Rent facilities
|
A
|
2
|
D
|
Build stands
|
A
|
5
|
E
|
Generator & wiring installation
|
C
|
2
|
F
|
Security
|
B
|
4
|
G
|
Lighting installation
|
E
|
2
|
H
|
Sound system installation
|
E, F
|
2
|
I
|
Stage construction
|
D
|
3
|
J
|
Tear down
|
G, H, I
|
4
|
• Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
• Identify all paths through the network. Which is the critical path?
• Which activities have slack time?
• Identify all burst activities and merge activities.
Activity 2
Given the following information, answer the questions about this project:
Activity
|
Expected Duration
|
Predecessors
|
A
|
4 days
|
-
|
B
|
9 days
|
A
|
C
|
11 days
|
A
|
D
|
5 days
|
B
|
E
|
3 days
|
B
|
F
|
7 days
|
C
|
G
|
3 days
|
D, F
|
H
|
2 days
|
E, G
|
I
|
1 day
|
H
|
• Draw the network as a Gantt chart.
• What is the critical path? Which activities have slack time?
• What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?
The response must include a reference list. Using Times New Roman 12 pnt font, double-space, one-inch margins, and APA style of writing and citations.