Using the complexity weighting scheme discussed in the slides and the information below, estimate the total functional point count. Assume historical data suggest 1 person-month equals five function points and 10 people can work on the project.
Component Types
|
Number
|
Complexity Rating
|
Number of Inputs
|
15
|
Average
|
Number of Outputs
|
30
|
Average
|
Number of Inquiries
|
20
|
High
|
Number of Files
|
35
|
15 files - High, 20 files - Average
|
Number of Interfaces
|
60
|
15 interfaces - Low, 25 interfaces - average, 20 interfaces - High
|
What is the estimated project duration?
What is the estimated team size if the project is to be completed in 6months?