What is the estimate at completion of the project


Problem

For the project with Earned Value (EV) = $350, Actual Cost (AC) = $300 and Planned Value (PV) = $400. The original project budget is $1,000. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the Estimate At Completion (EAC) of the project?

Request for Solution File

Ask an Expert for Answer!!
Project Management: What is the estimate at completion of the project
Reference No:- TGS03219136

Expected delivery within 24 Hours