Problem
1. What is the duration of the critical path of this network
2. What is the float for activity G
3. If a project manager proposes a finish time of 14 on teh project with no change in the start or activity durations, what is the total float of activity E.
|
Activity
|
Duration
|
Predeoesors
|
2
|
A
|
2
|
|
3
|
B
|
6
|
|
4
|
C
|
4
|
2,3
|
5
|
D
|
1
|
4
|
6
|
E
|
3
|
555
|
7
|
F
|
1
|
3
|
3
|
G
|
5
|
3
|
3
|
H
|
1
|
7,8
|
10
|
I
|
2
|
6,9
|