What is the document that is developed from the project scope statement, the project work breakdown structure (WBS), and the WBS dictionary?
A. Contract Management Plan.
B. Make-or-Buy Analysis.
C. Organizational Process Assets.
D. Statement of Work.
Note: I don't believe answer D is correct because as I understand the SOW is created before the WBS and dictionary? TIA for a well thought out res