Suppose that the company above is expected to finish the above project in 7 months. The company is to receive 10,000 dollars for each month they finish earlier, but will have to pay 25,000 dollars for each month they finish later than the expected 7 months. Let y denote the amount awarded to the company.
a- What is the distribution of y?
b- What is the expected value of y?